RESUME

 

 

 

 

 

 ACADEMICS                       :

 

QUALIFICATION

INSTITUTE

EXAMINING AUTHORITY

YEAR

SCORE & DIVISION

 

Diploma In Industrial Electronics.

Bharati Vidyapeeth’s Institute of Technology

Board Of Technical Examinations, Maharashtra State, Mumbai.

1988

68%

First Class

B.E

( Industrial Electronics)

Bharati Vidyapeeth’s College Of Engineering, Pune.

University Of Pune

1994

62%,

First Class

D.B.M

I.B.M.R, Parvati, Pune-411 037

University Of Pune

1995

First Class

M.M.S

I.B.M.R, Parvati, Pune-411 037

University Of Pune

1996

First Class

 

WORK EXPERIENCE :

 

Present Employer: M/s Tata Honeywell Ltd, Pune- 411 013.

 

TATA HONEYWELL, PUNE. (Based at Pune Office,) From March 1998, till Date:

 Designation: Assistant Manager (Field Services). (Installation and Commissioning Group.), Systems Division.

 

Job Profile & Responsibilities:  Installation and Commissioning of Turnkey C & I  Projects,involving DCS, PLCs, SCADA Systems, and Field Instrumentation of Tata Honeywell on sites, upto handing over of the Project site to the Customer. I believe that I possess good communication skills, coupled with leadership expertise, with me leading a team of engineers at different Site.

 

2) NOVEMBER 98 TO JAN 99:

 

Project : Coal  Dust Injection Project For Blast Furnace-6

(16    Tuyere*1800 TPH)

            

Job/Title/Responsibility : Commissioning Assistance to the Site Incharge for Installation and Commissioning.

 

3.GUJARAT GAS CORPORATION LTD. (GGCL)     Feb 99 to April 99.

 

Project: Gas Pipeline Scada                   

 

JobTitle/Responsibility : Installation and Powerup of Scada System.

Client                              :Gujarat Gas Corporation Ltd.,Surat

End-User Site                 : Gujarat Gas Corporation Ltd.,Surat.

 

Gujarat Gas Corporation Ltd.,Surat a premier Gas distribution Company, and an associate of British Gas, had laid a compressed Natural Gas pipeline from the port of Hazira to the township of Ankleshwar, passing through Barbodhan, Surat, Obha with 5 RTUs (remote telemetry unit) at each station. The length of this pipeline was 110 Kms, with 5 RTUs including 1MCR (Master Control Room, Surat).

 

4. August 99 till December 2000

 

Project: Cement Plant Expansion Project  (capacity  2500 TPD) 

JobTitle/Responsibility : Site Manger ( Installation and Commissioning).

 

Tata Chemicals Ltd., is one of India’s old leading manufacturer of a wide variety of chemical products. Such as a dense soda ash, ammonia iodized salt, detergent powder, and Portland and Flyash Based Cement. Etc. The cement plant expansion project was taken up in early1999 to upgrade its manufacturing capacity to 2500 TPD.

 

FORBES MARSHALL GROUP, PUNE.

 

(Employment Period: From October 95 till February 98).

 

Designation: Customer Support Engineer (Technical Services)

 

Job Profile & Responsibilities: On Site Installation and Commissioning of Process Control Instrumentation products and systems, calibration and repairs of same, on site + in-house.

 

PAST EMPLOYER         (First Employer)

 

(Employment Period: September  1993 to September 1995)

 

 

INSTRUMENT TECHNOLOGIES, Pune.

 

Designation : Instrumentation Engineer (Service).

Job Profile : Execution, Procurement of Instrumentation components viz. Transmitters, Sensors etc. and installing and commissioning them on customer’s sites.

Specific Experience :

Temperature Control Systems

Flow and Effluent Monitoring and Data Logging System.

·        Calibration of instruments and functional inspection on field.

 

 

 

 

 

 

 

ACADEMIC ACHIEVEMENTS     :

·        Final Year B.E. Project "Programmable Profile Temperature Controller" was nominated through B.V.C.O.E. at I.E.E.E. (Pune Chapter) State Level Competition.

 

PROFESSIONAL ASSOCIATIONS:

·        Member, I.E.T.E. Pune Centre Library.

·        Member, British Library.

·        In Process … ISA (Instrument Society of America), India Chapter.

 

SKILLS          :

·        Managing a team of Engineers, Technicians for installation, Commissioning loops checking, PLC ladder logic, programming.

·        Good logical skills, which will be utilised, better in DCS and PLC programming and debugging systems.